If you have comments and/or questions related to Vicksburg District’s Section 508 program or if you have concerns related to the Section 508 ICT accessibility of any content or the user interface on this website, please send an e-mail to VicksburgDistrict@USACE.Army.mil. Where applicable, please include in your e-mail the web address or URL and the specific accessibility barrier(s) you are encountering.

Interim Repairs continue at Arkabutla Dam

U.S. Army Corps of Engineers, Vicksburg District
Published June 24, 2024
Currently, drill pads are being installed for piezometers, automated instruments used for monitoring groundwater pressure. Relief wells, which act like valves to relieve the water pressure, allow excess water to be diverted safely, and serve to prevent sand boils, are scheduled to follow. The additional piezometers increase the USACE-MVK’s monitoring ability by sending data hourly to the technical team, allowing them to analyze conditions in real time.

Vicksburg, Miss – The U.S. Army Corps of Engineers Vicksburg District (USACE-MVK) continues to advance interim risk reduction measures (IRRM) at Arkabutla Dam in Northwest Mississippi. Contractor Frontier Services, Inc., began construction and equipment mobilization in early May. Currently, drill pads are being installed for piezometers, automated instruments used for monitoring groundwater pressure. Relief wells, which act like valves to relieve the water pressure, allow excess water to be diverted safely, and serve to prevent sand boils, are scheduled to follow. The additional piezometers increase the USACE-MVK’s monitoring ability by sending data hourly to the technical team, allowing them to analyze conditions in real time.

Vicksburg, Miss – The U.S. Army Corps of Engineers Vicksburg District (USACE-MVK) continues to advance interim risk reduction measures (IRRM) at Arkabutla Dam in Northwest Mississippi. Contractor Frontier Services, Inc., began construction and equipment mobilization in early May.  

Currently, drill pads are being installed for piezometers, automated instruments used for monitoring groundwater pressure. Relief wells, which act like valves to relieve the water pressure, allow excess water to be diverted safely, and serve to prevent sand boils, are scheduled to follow. The additional piezometers increase the USACE-MVK’s monitoring ability by sending data hourly to the technical team, allowing them to analyze conditions in real time.

Safety remains a top priority to the USACE Vicksburg District. Lake Staff and additional personnel are vigilantly monitoring the situation at Arkabutla Dam for any changes.  

Highway 51 Landing provides boating access into the Coldwater River above Arkabutla Dam and will remain the only open boat ramp at Arkabutla Lake. Camping and other recreational use of Arkabutla Lake area remain open, except for day use and fee use areas directly downstream of the dam.

The USACE Vicksburg District is engineering solutions to the nation’s toughest challenges. The Vicksburg District encompasses a 68,000-square-mile area across portions of Mississippi, Arkansas, and Louisiana, that holds nine major river basins and incorporates approximately 460 miles of mainline Mississippi River levees. The Vicksburg District is engaged in hundreds of projects and employs approximately 1,100 personnel.


Contact
Christi Kilroy
601-631-5000
VicksburgDistrict@usace.army.mil

Release no. 24-021